We're thrilled to be building the new Downtown Louisville Arena! When we're done, it'll be a rockin' 717,000 square feet of high-tech, high-energy space that will seat more than 22,000 people. It willl be home to the University of Louisville Men’s and Women’s Basketball teams, plus it'll be able to host a wide variety of other events including wrestling, swimming and volleyball, as well as concerts, circus, wrestling, boxing and ice shows.

The arena will also have a large plaza outside that can be used for additional events. The arena is being built on a "brownfield" site, which is land that used to be used for industrial or commercial reasons, and has been cleaned up and revitalized for a new purpose.



Schedule
October 2008 Site is cleared and ready for mobilization
November 2008: Mortenson signs safety agreement with OSHA
February 2009 - December 2009: Pour elevated concrete floor
September 2009 - April 2010: Erect stadium "steps" that shape the seating bowl
October 2009 - April 2010: Erect steel structure
August 2009 - May 2010:

Install exterior finishes, curtain wall & metal panel systems

May 2010: Complete roof, arena enclosed
May 2010 - October 2010: Install stadium seats
November 2010: Arena opens!




Customer:   Louisville Arena Authority

General Contractor:   Mortenson Construction

Construction Architect:
Populous

Start Date:   June 2008

Estimated Completion:   October 2010