Data Center Room
Fortune 500 Technology and Data Center Construction / Minneapolis SuburbMN
Can you renovate and expand a data center with uninterrupted operations?
In 2010, the fully operational building was expanded to add 55,000 GSF of building in two modules. This expansion was of particular significance to the customer as it required the expansion and integration of fully operating data center systems. This was accomplished through the intensive execution of a detailed Method of Procedure (MOPS) to ensure uninterrupted operating of the existing facility. The project was completed with zero operational downtime or incidents. 

Facts And Figures

Fortune 500 Company

Completed December 2011

55,000 GSF Raised Floor

Tier II

3.0 MW Critical Load

Delivery Methods

Guaranteed Maximum Price

The Team