Heavy Civil

team results

The Senate Wind Energy Project provides 150 megawatts of clean energy and consists of 119 GE 1.68 megawatt wind turbines.  Mortenson’s scope of work on the Senate project included the construction of 27 miles of access roads, turbine erection, 44 miles of underground collection, and construction of the O&M building.

Project stats:
–      75 Gamesa 2.0 Turbines
–      27 Miles of Access Roads
–      104,000 Tons of Aggregate Placed
–      150,000 Cubic Yards Excavated
–      245,000 Cubic Yards Cut/Fill
–      56,141 Man-hours

GET IN TOUCH

Eric Sellman Eric Sellman General Manager Email | 763.287.5559