This fast-track project involved the complete renovation of an existing 60,000 SF building to become the disaster recovery data center and mortgage service center for Alaska USA Federal Credit Union's lower 48 banking operations. The project involved the complete replacement of all electrical distribution from service entrance to parallel A/B data hall bussway distribution, and the build-out of 20,000 SF of data hall white space on raised access floor. Creative equipment procurement strategies were employed so that long lead equipment could be secured in time to meet tight schedule time frames.

Major equipment items provided were as follows:
- 1750KW emergency generator with 72-hour run-time fuel capacity
- Two (2) 500kVA UPSs for A/B power distribution
- 3000A main-tie-main switchboard
- Closed-transition transfer switch to allow for periodic loading of the emergency generator with building loads (no need for load bank)

The project's feature of passive, closed-transition transfer from utility to emergency generator and vice versa was a first in APS territory as the Utility had not previously allowed such an arrangement. Project was completed safely on-time and under-budget.

GET IN TOUCH

Bob Nartonis Bob Nartonis Senior Vice President Email | 763.287.5397
George Forristall George Forristall, LEED AP Development Executive Email | 480.839.5944