Upper School Reconstruction

team results

After the tragic explosion in Fall 2017 that displaced 351 students in Upper School campus, Minnehaha Academy endeavored to bring students back to their home as quickly as possible. Mortenson implemented a design-build delivery model that incorporated extensive input from Minnehaha Academy stakeholders and provided cost and schedule certainty. The result is a campus that includes vibrant and flexible spaces with abundant natural light to support various learning and teaching styles. The exterior materials were chosen to complement the palate of the existing campus, and the result is a foundation for an exceptional learning experience for the next generation of Minnehaha Academy students. 


Project Milestones

Pillar Raising Ceremony

8/2/2018

Utilities & Foundations Complete

08/2018

Structure Begins to Take Shape

09/2018

Enclosure Work Wraps-up

01/2019

Interior Finishes Complete

07/2019

Landscaping Begins

04/2019

School Begins at the Revitalized Campus

Fall 2019

GET IN TOUCH

Derek Hansen Derek Hansen Project Executive Email | 763.287.5838