Chisholm grid energy storage

Fort Worth, TX

Chisholm Grid Energy Storage

How do you build one of the first standalone energy storage systems in ERCOT?

Project Overview

Mortenson served as the balance of plant (BOP) and battery installation contractor for the Chisholm Grid Energy Storage project in Fort Worth, Texas. The project consists of a 100 MW containerized battery energy storage system and supporting power delivery infrastructure designed as a standalone resource in the ERCOT wholesale electricity market.

Customer Impact

Mortenson delivered the infrastructure and battery installation required for the 100 MW facility. At the start of construction, Chisholm Grid was identified as the largest standalone energy storage project under construction in the United States outside of California.

Key Takeaways:

  • 100 MW standalone, containerized battery energy storage system
  • Largest standalone battery energy storage project under construction in the United States outside of California when construction began
  • Mortenson’s ninth energy storage project
  • Approximately 50 personnel onsite during peak construction
  • Dallas-Fort Worth-based trade partners supported construction activities
Delivery Method

Balance of Plant

Related

Power Delivery

Energy Storage

Delivering Utility-Scale Energy Storage Infrastructure

Mortenson delivered the balance of plant infrastructure and battery installation for the 100 MW Chisholm Grid Energy Storage facility. The scope included the energy storage and power delivery systems required to support the standalone battery facility and its participation in the ERCOT wholesale electricity market.

Construction Execution

Following full notice to proceed in August 2020, Mortenson began construction of the balance of plant and high-voltage transmission infrastructure. Approximately 50 personnel were expected onsite at peak construction, with Dallas-Fort Worth-based trade partners supporting construction activities.

Supporting Energy Storage Market Growth

Chisholm Grid represented Mortenson’s ninth energy storage project, expanding the company’s experience delivering large-scale battery energy storage infrastructure.