Skip Navigation
Large-scale battery storage facility in desert

Crane, TX

Revolution Energy Storage

How do you build one of the largest energy storage projects in Texas?

Project Overview

Located in West Texas, the Revolution Energy Storage Project was delivered by Mortenson under a full engineering, procurement, and construction (EPC) contract for Spearmint Energy.

The project included a 150 MW/300 MWh battery energy storage facility, substation, and transmission line connecting the project to the Electric Reliability Council of Texas (ERCOT) grid.

Customer Impact

Spearmint Energy required utility-scale battery storage and grid interconnection infrastructure capable of supporting participation in the ERCOT market. Mortenson delivered the battery energy storage facility, substation, and transmission infrastructure required for commercial operation under a single EPC contract.

In addition to constructing the project, Mortenson supported Inflation Reduction Act (IRA) compliance efforts. Following project development, Spearmint Energy secured a $92 million tax equity investment through an Investment Tax Credit structure for the standalone battery energy storage system.

Key Takeaways:

  • Delivered a 150 MW/300 MWh battery energy storage project under a full EPC contract.
  • Designed and constructed the battery energy storage facility, substation, and transmission line connecting the project to the ERCOT grid.
  • Completed on schedule, within budget, and 100% injury-free.
  • Supported Inflation Reduction Act (IRA) compliance efforts.
Delivery Method

Engineer, Procure, and Construct

Related

Power Delivery

Energy Storage

San Antonio

Supporting Grid Reliability and Renewable Energy Integration

The completed 150 MW/300 MWh facility adds large-scale battery storage designed to support ERCOT grid reliability and resiliency by shifting renewable energy to periods of peak electricity demand. According to project documentation, the facility supports a low-cost, clean, and resilient grid serving homes and businesses throughout ERCOT.

Project Execution and Workforce Contribution

Approximately 42,000 working hours were contributed by Mortenson craft team members and trade partners during construction. The project was completed on schedule, within budget, and without recordable injuries.

Supporting Future Energy Infrastructure

Mortenson facilitated Inflation Reduction Act compliance efforts for Spearmint Energy as part of the Revolution Energy Storage Project.

Following project development, Spearmint Energy secured a $92 million tax equity investment provided through an Investment Tax Credit structure for the standalone battery energy storage system.