Mortenson's Energy Storage, Solar, and Power Delivery teams came together to build this utility-scale 20 MWac/30.8 MWdc single-axis PV solar plant, substation, and 10MW / 40MWhr battery energy storage system in Arizona. The lithium-ion battery system is set up for solar energy shifting to better meet peak demand needs and is Arizona's first utility-scale solar plus storage installation. The energy storage and substation were completed in 4 months on a very tight schedule.
Energy Storage
10MW
40MWhr
Pre-Engineered System
2 breaker substation
Solar
20 MWac/30.8 MWdc single-axis PV solar plant
Completed on schedule in 4 months
- Delivery Method
-
Engineer, Procure, Construct
- Additional Project Facts
-
10MW
40MWhr
Pre-Engineered System
Completion Date: April 2018