Aurora Data Center

 

This fast-track data centerbroke ground in June and completed in December 2015 -- one month ahead of schedule. The 18,000-square-foot data center is designed to be a Tier III and F3 rated facility. The center will reduce the impact of service interruptions to critical patient care systems in the event of a man-made or natural disaster and also, if necessary, serve as overflow space during disaster recovery.

The project also includes:

  • Two 1 Mega Watt Generators
  • 14 UPS’s & Associated Switchgear
  • Four Chillers
  • Two Free Coolers
  • 5000 SF of Raised Access Floor
  • Staging Space
  • Conference, Breakroom, & Command Center
Delivery Method

Design Build