Skip Navigation
Wind turbines along rural highway landscape

Medicine Bow, WY

TB Flats I & II Wind Project

Adding strength to Wyoming's wind power.

Project Overview

Mortenson constructed the 503.2 MW TB Flats I & II Wind Project in Medicine Bow, Wyoming. Spanning 44 square miles, the project consists of 132 Vestas wind turbines supported by two 230 kV substations, underground collection systems, and a 12-mile transmission line.  

Customer Impact

Rocky Mountain Power selected Mortenson to construct TB Flats I & II as well as the nearby Ekola Flats Wind Project, approximately 20 miles away. Constructing both projects concurrently created a coordinated approach across the two developments and helped bring the facilities into operation more efficiently. 

Key Takeaways:

  • 503.2 MW wind project spanning 44 square miles with 132 Vestas turbines.  
  • Mortenson self-performed foundation, collection, turbine erection and substation construction.
  • Constructed two 230 kV substations with five total main power transformers connected by a 12-mile transmission line. 
  • Installed 134.6 miles of underground collection trenching totaling 710,623 circuit feet. 
  • Turbine fleet includes 104 Vestas V136-4.3 turbines and 28 Vestas V110-2 MW turbines 
Delivery Method

Engineer, Procure and Construct

Related

Wind

Power Delivery

 
High voltage electrical substation in desert landscape

Building the Wind Project

TB Flats I & II includes 104 Vestas V136-4.3 turbines and 28 Vestas V110-2 MW turbines. Mortenson’s wind scope included turbine foundations, turbine erection and wiring, access roads, public road improvements, meteorological towers, collection systems, and an operations and maintenance building. Turbine erection began in April 2020.

Integrating the Power Delivery Infrastructure

The project’s electrical infrastructure included two 34.5 kV/230 kV substations, underground collection systems and a 12-mile transmission line connecting TB Flats I and II.

TB Flats I included 16 breakers, consisting of 13 collection feeders and three capacitor bank circuits, along with three main power transformers. TB Flats II included 10 breakers, consisting of eight collection feeders and two capacitor bank circuits, along with two main power transformers.

TB Flats I was energized in August 2020, followed by TB Flats II in November 2020.

Rural electrical substation under clear blue sky