Skip Navigation
Utility workers repairing overhead power lines

Falfurrias, TX

Alice to Falfurrias and Calallen to Stadium Transmission Line Rebuild Project

Rebuilding 64 miles of transmission line to bring reliable power to Texas communities. 

Project Overview

To support the reconstruction of a critical transmission corridor in southern Texas, AEP selected Mortenson to engineer, procure, and construct the rebuild of 64 miles of existing transmission infrastructure. The project upgraded the corridor from 69 kV to 138 kV class, rebuilt associated distribution infrastructure, managed right-of-way acquisition, and completed construction across active communities while maintaining a focus on customer communication and public safety.

Customer Impact

The project required extensive coordination with customers, landowners, local stakeholders, and community members throughout planning and construction. Approximately 20 miles of distribution underbuild remained energized while reconstruction activities were performed, requiring careful sequencing of work through six separate outage windows over more than fourteen months.

Construction took place across agricultural land, residential neighborhoods, urban environments, and areas adjacent to community facilities, including a high school. To help reduce impacts to homes and businesses, the project team managed customer notifications associated with distribution reconstruction activities and emphasized communication among AEP, Mortenson, trade partners, and the local community throughout planning, construction, and project closeout.

Key Takeaways:

  • Self-performed transmission structure installation, conductor installation, distribution line construction, and demolition of existing transmission facilities.
  • Reconstructed 64 miles of existing transmission infrastructure across southern Texas communities.
  • Upgraded the corridor from 69kV to 138kV class.
  • Removed existing single-pole and H-frame wood structures.
  • Rebuilt approximately 20 miles of energized distribution underbuild while construction activities were underway.
  • Executed construction through six separate outage windows spanning more than fourteen months.
  • Managed customer notifications to help reduce impacts to homes and businesses during reconstruction activities.
  • Completed construction with no public safety incidents.
Completion Date

April 2021

Delivery Method

Engineer, Procure, and Construct

Related

Power Delivery

Rebuilding Transmission Infrastructure

Utility workers repairing power lines with bucket trucks

The existing system consisted of single-pole and H-frame wood structures, many originally installed in 1928. The work included removal of existing transmission facilities, reconstruction of associated distribution infrastructure, and supplemental right-of-way acquisition along the corridor. Construction was executed through six outage windows spanning more than fourteen months.

Delivering Complex Construction Across Varied Environments

The transmission route crossed agricultural land, brush country, residential neighborhoods, and urban areas. One segment was constructed directly in front of a high school, while crews worked around existing water, sewer, electrical, and energized distribution infrastructure.

Upgrading the Corridor

The rebuilt corridor was upgraded from 69kV to 138kV class. New infrastructure included spun concrete tangent poles and custom steel angle and dead-end structures supported by drilled pier foundations. Mortenson installed 795 ACSS Drake conductor and 48-count OPGW throughout the corridor and self-performed transmission structure installation, conductor stringing, distribution line construction, and demolition of existing transmission facilities.

Utility workers in bucket trucks on pole
Utility poles and power lines against blue sky