Skip Navigation
Aerial view of large battery storage facility

Waco, TX

Jaguar Energy Storage Project

Strengthening the Texas power grid through energy storage.

Project Overview

The Jaguar Energy Storage Project represents a significant investment in utility-scale battery storage near Waco, Texas, with Mortenson serving as the engineering, procurement, and construction (EPC) contractor. The project included two co-located battery energy storage facilities totaling 300 MW/600 MWh, two 345 kV/34.5 kV substations, energy management system integration, and self-performed civil and energy storage construction. The project reached substantial completion in October 2025.

Customer Impact

The Jaguar Energy Storage Project combined energy storage and power delivery infrastructure to support utility-scale energy storage development in Texas. Mortenson delivered the balance of plant (BOP), energy management system (EMS), battery energy storage installation, and substation infrastructure required to support project operations.

In addition to serving the operating energy storage facilities, the project included a second substation designed to support future solar development, establishing infrastructure for future energy generation alongside the completed storage assets.

Key Takeaways

  • Served as EPC contractor for two co-located battery energy storage facilities totaling 300 MW/600 MWh.
  • Constructed two 345 kV/34.5 kV substations to support energy storage operations and future solar infrastructure.
  • Self-performed all civil site work, substation construction, and the majority of battery energy storage installation activities.
  • Mortenson Engineering Services designed substation foundations, structural steel, electrical systems, protection and control systems, and SCADA systems.
Completion Date

October 2025

Delivery Method

Engineer, Procure and Construct

Related

Civil

Energy Storage

Power Delivery

Delivering Utility-Scale Energy Storage Development

Mortenson was responsible for delivering the balance of plant and energy management system scopes for two co-located energy storage facilities totaling 300 MW/600 MWh. The work included civil site development, battery energy storage installation, substation construction, and supporting power delivery infrastructure.

Mortenson self-performed all civil site work and the majority of energy storage installation activities, allowing key scopes to be executed concurrently throughout construction.

Utility workers on lift at electrical substation
Aerial view of large battery storage facility

Integrating Energy Storage and Power Delivery Systems

Each energy storage facility included 46 Power Electronics inverters, rated at 4,200 kVA. Power conversion systems were supplied by Hithium battery energy storage system containers rated at 4.179 MWh each.

To support facility operations, Mortenson constructed two 345 kV/34.5 kV substations. The medium-voltage collection system operated at 34.5 kV, with main power transformers increasing voltage to 345 kV for transmission.

Substation 1 supported the completed energy storage facilities and included two main power transformers procured by Mortenson. Substation 2 was designed and constructed to support future solar infrastructure.

Integrated Engineering and Construction Execution

Mortenson Engineering Services designed the substations' foundations, structural steel, physical electrical systems, protection and control systems, and SCADA systems.

Construction of both substations was self-performed by Mortenson and executed concurrently with development of the energy storage yards, enabling coordinated delivery of both the energy storage and power delivery infrastructure.

Construction crew posing at electrical substation
Electrical substation silhouetted against colorful sunset